This project was built it two separate phases,
Phase 1 was the two 80’ dia silos, started in July of 07 and completed in April 0f 08.
Phase 2 was the 90’ dia silo, started in June of 10 and completed in September 10.
Caldwell provided complete engineering and project management. We built the silos complete from excavation, foundation and process tunnel construction, aeration product floor, silos walls and silo roof.